Development of 6-lane Delhi-Meerut Expressway

  • Project Details:  Divided into 4 packages;
    • 3 Pkg on Hybrid Annuity Mode; and 1 on EPC Mode;
    • Foundation stone laid on 31.12.2015;
    • Total Length = 82 km.
    • Total Cost = ~ 7500 Cr
  • Package I (6-lane Exp.+8-lane NH) :
    • Work commenced on 28.11.2016.
    • Work is Completed on 27.06.2018.
  • Package-II (6-lane Exp.+ +8-lane NH) :
    • Work commenced on 06.11.2017.
    • Scheduled Completion Date : 04.05.2020.
  • Physical progress of the work is 48%
    • Package-III (6-lane NH+ Service Road) :
  • Work commenced on 19.12.2016.
    • Scheduled Completion Date : 16.06.2019.
    • Physical progress of the work is 88%
      • Package-IV (6-lane Exp.) :
  • Work commenced on 27.02.2018.
  • Scheduled Completion Date : 20.08.2019.
  • Physical progress of the work is 44%.