Development of 6-lane Delhi-Meerut Expressway
- Project Details: Divided into 4 packages;
- 3 Pkg on Hybrid Annuity Mode; and 1 on EPC Mode;
- Foundation stone laid on 31.12.2015;
- Total Length = 82 km.
- Total Cost = ~ 7500 Cr
- Package I (6-lane Exp.+8-lane NH) :
- Work commenced on 28.11.2016.
- Work is Completed on 27.06.2018.
- Package-II (6-lane Exp.+ +8-lane NH) :
- Work commenced on 06.11.2017.
- Scheduled Completion Date : 04.05.2020.
-
Physical progress of the work is 48%
- Package-III (6-lane NH+ Service Road) :
- Work commenced on 19.12.2016.
- Scheduled Completion Date : 16.06.2019.
- Physical progress of the work is 88%
- Package-IV (6-lane Exp.) :
- Work commenced on 27.02.2018.
- Scheduled Completion Date : 20.08.2019.
- Physical progress of the work is 44%.