Research Schemes (Bridges)

A) Details of ongoing Bridge Research Schemes of this Ministry
(As on
|
S.No |
Name of Research scheme |
Executing Institute/Agency |
Particulars |
|
1 |
Creation of complete range of independent testing facilities for expansion joints at CRRI.(B-34) (F.No. RW/NH-34061/1/2005-S&R(B) |
Central Road Research Institute (CRRI) |
Sanctioned date: Revised target date of completion: Yet to be fixed Cost: Rs 580 lakhs Ministry’s share= 220 lakhs CRRI’s share = 360 lakhs |
|
2 |
Development of an expert system for distress diagnostics of concrete bridges (Fuzzy based) (B-35). (F.No. RW/NH-34061/2/2008-S&R(B) |
Indian |
Sanctioned date: Target date of completion: January, 2010 Cost: Rs50.00 lakhs |
|
3 |
Development of Standard Drawings for Composite girders (with steel girders) ) (B-36). (F.No. RW/NH-34066/2/2007-S&R(B) |
Institute for Steel Development and Growth (INSDAG). |
Sanctioned date: Target date of completion: December, 2009 Cost: Rs16.70 lakhs |
|
4 |
Development of Explanatory Commentary on Standard Specifications and Code of Practice for (F.No. RW/NH-34066/6/2008-S&R(B) |
Institute for Steel Development and Growth (INSDAG). |
Sanctioned date: Target date of completion: July, 2010 Cost: Rs11.30 lakhs Ministry’s share= 7.49 lakhs |
|
S.No |
Name of Research scheme |
Executing Institute/Agency |
Particulars |
|
5 |
Revision of Ministry’s Specifications for Roads and Bridges Works (B-38) (F.No. RW/NH-34066/9/2000-S&R(B) |
Indian Roads Congress (IRC) |
Sanctioned date: Target date of completion: October, 2010 Cost: Rs 40.00 lakhs |
|
6 |
Explanatory commentary for Code of Practice for concrete Road bridges (Limit State Method) (B-39) (F.No. RW/NH-35075/9/2006-S&R(B) |
Indian Roads Congress (IRC) |
Sanctioned date: Target date of completion: January, 2010 Cost Rs 14.00 lakhs |
|
7 |
Hydraulic investigations for design of raft foundations for bridges (B-40) (F.No. RW/NH-36087/1/2009-S&R(B) |
Indian |
Sanctioned date: 28th May 2009 Target date of completion: June, 2011 Cost: Rs 22.008 lakhs |
|
8. |
Static and Dynamic Load Test for piles (B-41) (F.No. RW/NH-34075/1/2009-S&R(B) |
Indian |
Sanctioned date 23rd July, 2009 Target date of completion July 2011 Cost Rs.26.00 lakhs |